Sisi Nubi Phase 2

Client

Total E & P Indonesia
Project Name Sisi Nubi Phase 2 - EPCI Contract 1
Project Description

Sisi Nubi Phase 2 is a further development of Sisi and Nubi field, the objective of the Sisi Nubi Phase 2 development is to provide additional wells on existing slots or from new slots provided by installing platform extensions which allows additional production in 2011 to mitigate the short term Sisi Nubi production decline.

In the scope of Sisi Nubi Phase 2, 12 additional wells will be drilled from new and exisiting slots, which should be available at third quarter of 2011. Platform extensions are proposed on 2 platforms, WPN2 and MWPS platforms to accomodate 4 additional slots and drill up to 14 new development wells.

Contract Award November 2010
Scope Engineering, Procurement, Construction, Hook-Up, Pre-Commissioning and Commissioning Assistance
Project Location Sisi Nubi Field, Mahakam Delta, East Kalimnatan
Scope of Work

Fabrication and Installation of CP Protection Frame at MWPS Platforms

Fabrication and Installation of CP Guide and Deck Extension at WPN2 and MWPS platforms

Fabrication and Installation of Production Header, Test Header and HP Vent Headers at WPN2 and MWPS platforms

Fabrication and Installation of Fuel Gas Filters

Fabrication and Installation of Cathodic Protection System

Fabrication and Installation of Flow Lines up to the last spool at WPN2 and MWPS platforms

Fabrication and Installation of Utilities Lines (deluge fire water, closed drain, open drain and methanol injection) at WPN2 & MWPS platforms

Modifications of PCS, SSS and F&G Systems at WPN2 and MWPS

Installation and integration of new WHCP Module at WPN2 and MWPS platforms, with modification of control system (interconnection and re-programming PCS, SSS & MTU).

Installation and integration of HPU extensions at WPN2 and MWPS

Additional lightings on Platform extension area

Mud Mat Demolition works

Saturation and Air Diving works

Heavy Lift Activities

Perform NDE and testing

Pre-Commissioning works of all installed lines and its utilities

Commissioning Assistance

Water Depth 40 to 65 m
Project Completion November 2011