Capabilities
Our Core BusinessProjectsAchievements & Awards

South Mahakam Phase 3

Client TOTAL E & P INDONESIA
Project Name South Mahakam Phase 3 (SMK3) Project
Project Description

To produce the South Mahakam Gas Condensate Field which will supply to the Bontang LNG PLant and to Kaltim Industrial Estate

Contract Award April 2013
Scope

Engineering, Procurement, Construction, Hook-Up, Commissioning, and Start-up

Project Location Located offshore, approximately 35 km to the South-East of Balikpapan and 58 km South of the nearest Peciko platform 'SWP-F' (Peciko 5b)
Facilities

Jempang Metulang (JM1) Platform - Tripod Jacket, Topside 6 Slots with 7 Wells (Associated equipment like Pressure Vessels, Piping, Multiphase Measurement, Control Valves, Field Instruments, and Integrated Control and Safety System)

MD1 Tie-In Pig Receiver, Pre-Fabricated Tie-In Spools, Valves, Gas Detectors, ICSS Modification

Onshore (Senipah) Control System Modification for New Platform

Water depth Ranges between 45 m to 60 m
Project Completion April 2015